Wakiso GKMA Road Projects Pushed to 2027 Over Construction Delays

The completion timeline for three major road projects in Wakiso under the GKMA programme has been extended to 2027 due to heavy rainfall, fuel shortages, and rising costs. Source: https://nilepost.co.ug/news/390398/wakiso-gkma-road-projects-pushed-to-2027-over-construction-delays

Commuters and residents in Wakiso District will have to wait longer for better infrastructure after the completion date for three major road projects under the Greater Kampala Metropolitan Area (GKMA) programme was officially pushed to 2027.

Originally slated for completion in November 2026, the projects covering Bukasa–Ssentema, Kakiri, and Kitemu–Kisozi–Naggalabi–Buddo roads have fallen behind schedule. According to project supervisors, contractors have struggled to maintain their planned construction pace.

Engineer Nashir Sseguya, who oversees the Bukasa–Ssentema Road works, pointed out that persistent heavy rainfall, critical fuel shortages, and surging fuel prices have severely hampered operations on the ground. These hurdles have not only plagued Wakiso but have created bottlenecks for road construction initiatives across various regions of Uganda.

Following these setbacks, the supervising team escalated the matter to the Permanent Secretary in the Ministry of Works and Transport. Consultations are now underway to officially extend the implementation period, granting contractors the necessary time to absorb the shocks and finalize the infrastructure developments.

The delay has sparked growing frustration among local residents and leaders who were eagerly anticipating the relief that improved transport networks would bring. With significant work still unfinished, communities along the affected corridors must contend with prolonged disruptions.